Monday 2 April 2012

Day 52 - 2nd of April 2012. Not much has happened on site this week, apart from a meeting with the hydronic heating plumber where we went through radiator locations throughout the house. We made a few modifications to sizes and locations of the radiators given certain restrictions on window height and so forth. Our site supervisor was very accommodating, offering to make small modifications to ensure the radiators fit.   We can understand why Mainvue have decided not to pursue hydronic heating  given its complexity. The roof guards have been removed and all the upstairs windows have been installed. We have been told the bricklayers will be on site this Wednesday, hopefully to make a start.